Deer Valley Road

Map showing project area of construction project TT0248 Deer Valley Road
Page header showing logo and title Building Deer Valley Road connecting El Mirage Road to 109th Ave

Project Overview

The Deer Valley Road project (TT0248) will construct an east-west arterial crossing the Agua Fria River. The project will widen and extend Deer Valley Road and Williams Drive across the Agua Fria River for 2.5 miles from El Mirage Road to 109th Avenue. Other improvements include storm drain installation, drainage basins, landscaping and irrigation.

Project Features

  • Construct a connection between the east end of Williams Drive at 117th Avenue to the west end of Deer Valley Road at 109th Avenue.
  • Widen Williams Drive between El Mirage Road and 117th Avenue.
  • Install roundabouts at both 117th Avenue and at 109th Avenue.
  • Increased safety for pedestrians - HAWK crossing at 119th Avenue.

Project Milestones

  • Construction Start: June 28, 2021
  • Construction Completion: Fall 2022

Project Newsletters

Stay Informed about the Deer Valley Road project. Sign up here to receive future project newsletters.

June 2021

Construction Progress

Construction Notice to Proceed: June 28, 2021

(**Schedule is subject to change for reasons beyond MCDOT’s control, including:weather, equipment failure, illness or other circumstances. **)

For additional project information, contact MCDOT at MCDOTProjects@maricopa.gov or at (602) 506-3342.