Remediation Activities

2/5

Soil Vapor Extraction (SVE)

STATUS AS OF 10/10/2022 - FULLY FUNCTIONAL AND OPERATING

Soil vapor extraction, or “SVE,” extracts (removes) contaminant vapors (VOCs or volatile organic compounds) from below ground for treatment above ground. Vapors are the gases that form when chemicals evaporate. SVE extracts vapors from the soil above the water table by applying a vacuum to pull the vapors out. The air is then filtered through a series of filtration tanks before being discharged. Discharged air meets all applicable air quality standards.

Since full scale start up in September of 2015, the SVE has extracted approximately 47,964 pounds of VOCs.  Monitoring indicates an overall decrease in TCE concentrations at all soil vapor depths.


Groundwater Treatment System (GWTS)

STATUS AS OF 12/5/2022 - UNDER CONSTRUCTION (see each phase for details)

Phase I - Groundwater Treatment Facility (complete)

The Groundwater Treatment Facility is complete. Because the GWTS Phase 3 infrastructure is still in the process of being constructed, the treatment facility is not operating at this time. As of 9/1/2021, this facility was complete and ready for operation once the other phases are complete.

Phase II - Conveyance Pipeline (complete)

Construction is complete. The sub-grade, 8-inch diameter pipe has been installed from the Groundwater Treatment Facility (on the landfill property) to the injection well located on City of Phoenix property at 4050 E Sleepy Ranch Road.

pipe

Phase III - Injection Well (under construction)

There are three sub-phases to Phase III

Phase III, Sub-phase A (complete) is the well itself. The well has been drilled and developed to a depth of 1,600 feet below surface level. Once the entire system is complete, clean water will be injected into the groundwater at a depth of greater than 1,000 feet below surface level. The pump will be submerged in the well approximately 1,000 feet below the surface.

Phase III, Sub-phase B (under construction) is the well security and screening. Neighbors around the 4050 E Sleepy Ranch Road well site have worked with the County to ensure a decorative wall and landscaping. Site components will be kept below the wall height. The injection pump will be a submergible pump installed some 1,000 feet below the surface. (Note: picture is a rendering only and is not intended to show detailed features.)

Construction of the wall is complete and planting of trees and shrubs on three sides is complete. The last of the landscaping will be restored once the final utility work has also been completed. Estimated for December 2022.

wall

Phase III, Sub-phase C (under construction) is the equipment necessary for the injection process. It includes a submergible pump, an electrical vault, a partially underground tank, and piping. Some components must be custom designed and built to keep the equipment profile below the screening wall height. In an effort to minimize the impact to the residents, the electrical service will be bored rather than be installed using an open trench. The wellhead vault has been delivered and will be installed beginning in late April or early May. See Well Site at 4050 E Sleepy Ranch Road drawing in the "Maps and Images" tab or click the image to the right.

Delays in installing the APS power feed to the site continue to pose problems and have pushed the anticipated completion of Phase III into December of 2022


undefined Opens in new window

New Well Installations

STATUS AS OF 12/5/2022


The next monitoring well installations are planned for the Summer of 2023. 


Well Location Map 2022 Opens in new window